|
Pilling
Stage 1 of construction for an industrial seawater intake basin
cofferdam in the Gulf region was the installation of 800 mm diameter
heavily reinforced cast-in-place bored piles at 900 mm centres.
Tight tolerances for pile location and verticality were met by sinking
6,5 m long temporary casings with a vibrator through a concrete
template. The piles were bored to between 12 and 19 m on a "hit-and-miss"
basis; 48 hours elapsed between concreting of adjacent piles. After
boring and cleaning out, prefabricated reinforcement cages and high
slump concrete were placed using tremie techniques and the casing
withdrawn using a vibrator. In 4 piles, tubes were inserted for installation
of inclinometers. In 62 working days 276 No. piles were installed,
274 tonnes of steel fixed and 2,130 m³ of concrete poured.
Wing
Jet Grouting
Whilst piles and anchors were suffficient to prevent collapse, water
tightness was required to seal the pile wall joints.
Soilcrete-Wing Jet
Grouting was used between piles. This technique consisted of predrilling
holes through a top 1.5 m casing to av. 10.8 m, stabilising with
a bentonite suspension, lowering of hollow stem rods fitted with
a special tip and pumping of cement grout at 300 bars pressure as
the rods were slowly withdrawn. At this pressure, the grout formed
a "V" shaped column behind the pile joints. For the wing wall joints,
Soilcrete(®) techniques were used to form circular grout columns. In
42 days 2908 m of holes were predrilled and 1 million litres of
grout injected.
|